Application KET/2009/0549
Field Name | Details |
---|---|
Applicant Name | Infinergy Limited |
Location | New Albion Wind Farm Towns Close Farm (land at), Rushton |
Ward | Welland |
Proposal | Erection of 7 no. wind turbines (100m high to the tip of a rotor blade in a vertical position). Provision of crane hard standings, control building, substation, underground cabling, temporary construction compound, widening of the existing site access, new site access tracks and permanent 65m high anemometer mast |
Application Type | Full Application with EIA |
Case officer | Anne Dew 01536 534316 |
Decision level description | Full Planning Committee |
Event | Date |
---|---|
Date received | 29/09/2009 |
Validation/registration date | 29/09/2009 |
Statutory expiry date | 19/01/2010 |
Neighbours/Consultations sent on | 15/12/2009 |
Expiry date for neighbours/consultations | 06/01/2010 |
Advertised on | 15/10/2009 |
Expiry date for advertisement | 05/11/2009 |
Target Decision Date | 19/01/2010 |
Committee Date (check for report in Downloads below or in Meetings and Minutes) | 19/01/2010 |
Decided on | 20/01/2010 |
Decision | Approved |